暗挖车站地下连续墙施工地表沉降分析
引用本文:朱雅倩,薛洪松,刘希胜,杜昌隆,赵旭,张志红. 暗挖车站地下连续墙施工地表沉降分析[J]. 岩土工程技术, 2021, 0(2): 77-83,98
作者姓名:朱雅倩  薛洪松  刘希胜  杜昌隆  赵旭  张志红
作者单位:北京工业大学城市与工程安全减灾教育部重点实验室;北京建工集团有限责任公司
基金项目:国家自然科学基金面上项目(41672289);国家自然科学基金重点项目(51538001)。
摘    要:工程建设中地下水资源保护问题一直是社会各界关注的焦点.以国内首例城市地铁PBA暗挖车站边导洞内施工地下连续墙止水工程为依托,采用MIDAS/GTS NX软件重点模拟了导洞内地下连续墙施工前、施工中及施工后的地表沉降变化规律,并与现场监测数据进行对比分析.结果表明:1)地下连续墙施工前,地表沉降曲线以车站中线为中心,呈明...

关 键 词:PBA  边导洞  地下连续墙  地表沉降

Analysis on the Ground Settlement in the Construction of Diaphragm Wall of Subway Excavated Stations
Zhu Yaqian,Xue Hongsong,Liu Xisheng,Du Changlong,Zhao Xu,Zhang Zhihong. Analysis on the Ground Settlement in the Construction of Diaphragm Wall of Subway Excavated Stations[J]. Geotechnical Engineering Technique, 2021, 0(2): 77-83,98
Authors:Zhu Yaqian  Xue Hongsong  Liu Xisheng  Du Changlong  Zhao Xu  Zhang Zhihong
Affiliation:(The Key Laboratory of Urban Security and Disaster Engineering,Ministry of Education,Beijing University of Technology,Beijing 100124,China;Beijing Construction Engineering Group,Beijing 100055,China)
Abstract:The protection of groundwater resources has always been a focus in engineering construction.This analysis is based on an underground diaphragm wall water stop project,which is the first construction in the side pilot tunnel of PBA underground excavation station of urban subway in China.MIDAS/GTS NX software is used to simulate the ground settlement changes of the diaphragm wall construction in the pilot tunnel,including before construction,during construction and after construction,and the results are compared with the actual field monitoring data.The results show that:(1)before the construction of the diaphragm wall,the center line of the surface settlement curve is the center line of the station,and the distribution of the curves is obvious symmetrical settlement groove.(2)During the construction of diaphragm wall,when the construction of one-sided diaphragm wall is completed,the settlement near the surface above is the most obvious.The maximum increment account is about 25%of the total settlement.(3)After the construction of diaphragm wall on the left and right sides,the incremental curve of surface settlement amount is similar to W-type.(4)After the construction of 6 diaphragm walls on the left and right sides,the settlement on the surface above tends to be stable,and the settlement rate basically remains unchanged.
Keywords:pile-beam-arch method  pilot tunnel  diaphragm wall  surface settlement