首页 | 官方网站   微博 | 高级检索  
     

宝泉抽水蓄能电站上水库工程设计
引用本文:景来红,杨顺群. 宝泉抽水蓄能电站上水库工程设计[J]. 人民黄河, 2002, 24(6): 24-25
作者姓名:景来红  杨顺群
作者单位:黄河水利委员会,勘测规划设计研究院,河南,郑州,450003
摘    要:宝泉抽水蓄能电站装机容量1200MW,由上水库,输水发电系统和下水库等建筑物组成。上水库大坝采用沥青混凝土面板堆石坝,库盆采用全面防渗方案,以减少渗漏损失,设计优化后上水库工程采用的工程布置方案,不仅对工程施工和施工导流十分有利,而且还有效地解决了超标准洪水和固体径流问题。

关 键 词:宝泉抽水蓄能电站 水库工程 工程设计 防渗
文章编号:1000-1379(2002)06-0024-02

Engineering Design in the Head Reservoir at Baoquan Pumped Storage Station
JING Lai-hong,YANG Shun-qun. Engineering Design in the Head Reservoir at Baoquan Pumped Storage Station[J]. Yellow River, 2002, 24(6): 24-25
Authors:JING Lai-hong  YANG Shun-qun
Abstract:The installed capacity at Baoquan Pumped Storage Station is 1 200 MW composed of the head reservoir, system of power generation with water and the tail reservoir. The rock-fill dam with asphalt concrete facing is used in the head reservoir dam, the overall anti-seepage scheme is used in the reservoir basin in order to reduce seepage loss. After the design optimization, the engineering arrangement scheme used in the head reservoir project not only is very beneficial to engineering construction and construction diversion but also solve problems about exceeding standard flood and sediment runoff effectively.
Keywords:arrangement  seepage  dam and reservoir  Baoquan Pumped Storage Station