摘    要:首先介绍了承压水对深基坑工程的影响,其次系统阐述了天津地铁新开路站降压井的设计与施工技术要点,最后从现场监测情况分析了降水设计的合理性,以积累降压井设计施工经验,保证工程施工的顺利进行。

关 键 词:承压水  降压井  设计  施工  监测

The water lowering well design and construction of Tianjin subway Xinkai road station
CUI Cheng. The water lowering well design and construction of Tianjin subway Xinkai road station[J]. Shanxi Architecture, 2010, 36(2): 136-137
Authors:CUI Cheng
Abstract:The confined water influences on deep excavation engineering was introduced at first,then the water lowering well design and construction points of Tianjin subway Xinkai road station were illustrated systematically.At last,the dewatering design rationality was analyzed from site monitoring situation,so as to accumulate water lowering well design construction experience and guarantee engineering construction smoothly running.
Keywords:confined water  water lowering well  design  construction  monitoring  