水电站PLC系统双I/O冗余输入输出解决方案 |
| |
引用本文: | 易春辉,李天石,刘锦.水电站PLC系统双I/O冗余输入输出解决方案[J].水力发电,2003,29(11):44-45,56. |
| |
作者姓名: | 易春辉 李天石 刘锦 |
| |
作者单位: | 1. 西安交通大学,陕西,西安,710049;西安航天自动化股份有限公司,陕西,西安,710065 2. 西安交通大学,陕西,西安,710049 3. 西安航天自动化股份有限公司,陕西,西安,710065 |
| |
摘 要: | 在水电站工业自动化控制中,针对现场高可靠性应用场合,PLC系统往往采用双I/O冗余输入输出。双I/O冗余输入输出不能简单地直接串并联,必须根据信号的类型、信号等级、输入输出方式不同,分别解决。对于模拟量输出冗余还应注意切换过程的扰动情况。
|
关 键 词: | 水电站运行 PLC I/O双冗余 模拟量输入输出 切换扰动 |
文章编号: | 0559-9342(2003)11-0044-02 |
The solution of the dual I/O PLC control system of hydropower station |
| |
Abstract: | In the application of the high reliable control projects of hydropower station, the dual I/O PLC control method is normally adopted. Dual I/O signals can not be connected simply in series or parallel. Different kinds of signal have different solutions. Special attention must be paid to the switch of dual analog output signals for the potential switch disturbance. |
| |
Keywords: | operation of hydropower station PLC dual I/O redundancy analog input and output switch disturbance |
本文献已被 CNKI 维普 万方数据 等数据库收录! |
|