新建或迁建血站正式运行前的确认工作探讨
引用本文:骆展鹏彭楷许茜代华友杨丹蓉杨春燕杨冬燕黄霞.新建或迁建血站正式运行前的确认工作探讨[J].中国卫生质量管理,2021,0(5):092-94.
作者姓名:骆展鹏彭楷许茜代华友杨丹蓉杨春燕杨冬燕黄霞
作者单位:重庆市血液中心
摘    要:在迁建新业务大楼正式投入运行前,采用质量审核、试运行、目视检查等方法,分阶段确认新建血站的基础设施、设备、环境、工作流程等是否达到预期要求,探讨新血站系统化确认方法。新建或迁建后的血站在正式启用前应对其所涉及的建筑设施、设备、环境、工作流程等进行全面且系统的确认,以更好地保障血液质量与安全。

关 键 词:血站  新建  迁建  系统化  确认

Confirmation of New or Relocated Blood Stations before Formal Operation
LUO Zhanpeng,PENG Kai,XU Qian.Confirmation of New or Relocated Blood Stations before Formal Operation[J].Chinese Health Quality Management,2021,0(5):092-94.
Authors:LUO Zhanpeng  PENG Kai  XU Qian
Affiliation:Chongqing Blood Center, Chongqing
Abstract:Before the new business building was formally put into operation, the quality audit, visual inspection, trial operation and other methods were adopted to confirm whether the infrastructure, equipment, environment and work flow of the new blood station met the expected requirements by stages, and the systematic confirmation method of the new blood station was discussed. In order to better guarantee the quality and safety of blood, a comprehensive and systematic confirmation should be carried out on the construction facilities, equipment, environment and work flow involved in the newly built or relocated blood stations before official operation.
Keywords:Blood Station  New Construction  Relocation  Systematization  Confirmation