基于坝面作业仿真的面板堆石坝施工进度优化研究
引用本文:赵春菊,胡超,周宜红.基于坝面作业仿真的面板堆石坝施工进度优化研究[J].水利水电技术,2014,45(9):65.
作者姓名:赵春菊  胡超  周宜红
作者单位:(1.三峡大学水利与环境学院,湖北宜昌443000;2.武汉大学水利水电学院,湖北武汉430072; 3.三峡地区地质灾害与生态环境湖北省协同创新中心,湖北宜昌443000)
摘    要:在传统的面板堆石坝施工过程仿真计算的基础上,建立了基于坝面作业的面板堆石坝施工仿真系统。根据坝面大小及施工方式分别建立流水作业与顺序作业的施工仿真模型,研究不同作业方式中时间参数的计算方法,采用离散事件系统仿真理论建立了面板堆石坝施工仿真系统。采用该系统对某面板堆石坝工程的施工方案进行了分析验证,对工程工期进行分析计算,证明该系统可对工程的施工管理和决策提供支撑。

关 键 词:面板堆石坝  坝面作业  施工仿真  进度优化  
收稿时间:2013-10-29

Study on optimization of construction progress of concrete face rock-fill dam based on simulation of working on dam construction surface
ZHAO Chunju,HU Chao,ZHOU Yihong.Study on optimization of construction progress of concrete face rock-fill dam based on simulation of working on dam construction surface[J].Water Resources and Hydropower Engineering,2014,45(9):65.
Authors:ZHAO Chunju  HU Chao  ZHOU Yihong
Affiliation:(1. College of Hydraulic and Environment Engineering,China Three Gorges University,Yichang443000,Hubei, China; 2. School of Water Resources and Hydropower Engineering,Wuhan University,Wuhan430072,Hubei, China;3. Collaborative Innovation Center for Geo-Hazards and Eco-Environment in Three Gorges Area of Hubei Province, Yichang443000,Hubei, China)
Abstract:Based on the simulating calculation for the construction process of the conventional concrete face rockfill dam, a construction simulation system for the dam is established on the basis of the working on the dam construction surface. In accordance with the size of the dam construction surface and the construction method, the construction simulation models for both the streamline working and the sequential working are respectively established, and then the methods for calculating the time parameters for the different working modes are studied, furthermore, the simulating system for the construction of the dam is set up with the simulation theory for the discrete event system. Moreover, the construction scheme of a project of concrete face rockfill dam is analyzed and certified with this system, in which the construction period of the project is analyzed and calculated and it is proved that this system can provide supporting for both the construction management and decision-making of the project.
Keywords:concrete face rockfill dam  working on dam construction surface  construction simulation  progress optimization  