图珲公路高填方涵洞竖向荷载分布试验研究
引用本文:王雯璐,赵江鹏,赵大军,王磊.图珲公路高填方涵洞竖向荷载分布试验研究[J].地下空间与工程学报,2014,10(4):794-798.
作者姓名:王雯璐  赵江鹏  赵大军  王磊
作者单位:1. 吉林大学建设工程学院,长春 130026;2.河南工程学院资源与环境学院,郑州 451191;3.中煤科工集团西安研究院,西安 710054
基金项目:国家重点基础研究发展计划“973”资助项目(2010CB731503)
摘    要:为了研究高填方涵洞顶部土压力随填土高度变化的规律以及拱效应,依据相似原理设计了宽坦沟谷沟心设涵边界条件的涵洞室内模型试验,测得不同填土高的涵洞顶部土压力和涵台外侧土压力;选取图们—珲春高速公路桩号为RK392+640处高填方涵洞作为试验涵洞,在涵顶埋设土压力盒测量不同填土高度的涵顶竖向土压力;按照《公路桥涵设计通用规范(JTG D60-2004)》计算土压力,比较并分析计算值与实测值的误差。结果表明,涵顶土压力随着填土的增加而增加,当填土达到一定高度后,高填方涵洞上方将产生拱效应,由于涵顶路基填料的特点,拱效应具有不稳定性,从而使土压力的增加幅度变小,涵顶土压力也随填土高度呈现非线性规律变化。

关 键 词:高填方涵洞  室内模型试验  现场测试  土压力  拱效应  
收稿时间:2014-03-26

Experimental Study on Vertical Load Distribution of High-Stacked Culverts at Tumen-Hunchun Highway
Wang Wenlu,Zhao Jiangpeng,Zhao Dajun,Wang Lei.Experimental Study on Vertical Load Distribution of High-Stacked Culverts at Tumen-Hunchun Highway[J].Chinese Journal of Underground Space and Engineering,2014,10(4):794-798.
Authors:Wang Wenlu  Zhao Jiangpeng  Zhao Dajun  Wang Lei
Affiliation:1. College of Construction Engineering, Jilin University, Changchun 130026, China;2. Resources and Environmental Engineering Department, Henan Institute of Engineering, Zhengzhou 451191, China;3. Xi’an Research Institute, China Cool Technology and Engineering Group Corp, Xi’an 710054, China
Abstract:Based on the similarity principle, for the boundary conditions of culvert located in wide valley, the laboratory model tests on culvert were designed to measure the earth pressure on culvert and culvert pier under different fill heights to find the improvement of fill on the earth pressure of high-stacked culvert and arching action. The earth pressure cells were buried on the top of high-stacked test culvert located at pile RK392+640 of Tumen-Hunchun highway to measure the vertical earth pressure under different fill heights. Meanwhile the calculations of earth pressure according to the General Code for Design of Highway Bridges and Culverts (JTG D60-2004) were obtained. The errors between the calculation results from Code and the measured results were analyzed. The results show that the earth pressure on culvert increases with the increasing of fill height, as the earth embankment is filled higher, the arching action will take place above the culvert. Because the fill is different from the rock, the arching action is unstable. The growth of the earth pressure reduces gradually and the earth pressure varies non-linearly.
Keywords:high-stacked culvert  laboratory model test  field test  earth pressure  arch action  
点击此处可从《地下空间与工程学报》浏览原始摘要信息
点击此处可从《地下空间与工程学报》下载全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏