湘钢热电厂75t/h煤粉锅炉改烧煤气时的受热面调整与燃烧器改造
引用本文:陈冬林,鄢晓忠,符慧林,夏候国伟,刘亮,严集成,汤海军,林建湘. 湘钢热电厂75t/h煤粉锅炉改烧煤气时的受热面调整与燃烧器改造[J]. 发电设备, 2002, 13(1): 18-22,26
作者姓名:陈冬林  鄢晓忠  符慧林  夏候国伟  刘亮  严集成  汤海军  林建湘
作者单位:1. 长沙电力学院,湖南,长沙,410077
2. 湖南省湘潭钢铁公司热电厂,湖南,湘潭,411100
摘    要:湘潭钢铁公司热电厂为回收低热值高炉煤气 ,对一台 75t/h煤粉炉进行了全烧煤气改造。在炉内换热三维数值计算及全面校核热力计算的基础上 ,提出了改造方案。改后现场测试结果是 :全烧煤气时锅炉出力可达 78t/h ,锅炉热效率大于 80 % ,排烟温度低于 180°C ,过热汽温未出现超温现象 ,风机出力满足要求 ;煤、气混烧时出力可达 88t/h。改造达到了预期的目标。图 8表 7参 5

关 键 词:煤粉锅炉  高炉煤气  受热面调整  燃烧器改造
文章编号:1671-086X(2002)01-0018-05

Heating Surface Rearrangement and Burner Reconstruction of a 75t/h Boiler for a Fuel-change from Pulverized Coal to Blastfurnace Gas in Xiang-Steel''''s Cogeneration Power Plant
CHEN Dong lin ,YIAN Xiao zong ,FU Hui lin ,XIAHOU Guo wei ,LIU Liang ,YIAN Ji cheng ,TANG Hai jun ,LIN Jian xiang. Heating Surface Rearrangement and Burner Reconstruction of a 75t/h Boiler for a Fuel-change from Pulverized Coal to Blastfurnace Gas in Xiang-Steel''''s Cogeneration Power Plant[J]. Power Equipment, 2002, 13(1): 18-22,26
Authors:CHEN Dong lin   YIAN Xiao zong   FU Hui lin   XIAHOU Guo wei   LIU Liang   YIAN Ji cheng   TANG Hai jun   LIN Jian xiang
Affiliation:CHEN Dong lin 1,YIAN Xiao zong 1,FU Hui lin 1,XIAHOU Guo wei 1,LIU Liang 1,YIAN Ji cheng 2,TANG Hai jun 2,LIN Jian xiang 2
Abstract:For the purpose of recovering the heat contained in blast furnace gas of low beating value, a 75t/h pulverized coal boiler of the cogeneration power plant of Xiangtan Steel Co. has been retrofitted for burning blast furnace gas exclusively. Before that a retrofit project was put forth, following a preceding 3 dimensional digital heat transfer calculation for the interior of the boiler and an overall check of the thermal calculation. Ultimate on site test measurements showed that: using blast furnace gas exclusively, a boiler output of 78t/h can be attained with a boiler thermal efficiency more than 80% and a stack gas temperature below 180 °C . The superheater didn't show any sign of overheating, and the air fan output was able to satisfy requirements. The output attained eith mixed combustion of gas and coal was 88t/h. Thus, the expected aim of retrofit was arrived at. Figs 9, tables 7 and refs 5
Keywords:pulverized coal boiler  blast furnace gas  heating surface rearrangement  burner reconstruction