首页 | 官方网站   微博 | 高级检索  
     

山西引黄工程南干线7# 隧洞衬砌外水压力研究
引用本文:李雪春,陈重华,陈平,徐昕. 山西引黄工程南干线7# 隧洞衬砌外水压力研究[J]. 中国水利水电科学研究院学报, 2003, 1(3): 200-206
作者姓名:李雪春  陈重华  陈平  徐昕
作者单位:中国水利水电科学研究院,结构材料研究所,北京,100038
摘    要:本文采用综合修正系数取代规范建议的单一折减系数,用渗流场分析方法确定作用在引黄入晋南干线7#隧洞衬砌上的外水压力。由己知钻孔水位及泉水位反演出各地层的渗透张量及地表入渗强度求得初始渗流场。衬砌外水压力分析中考虑了衬砌混凝土的渗透性以及排水、灌浆等工程措施的影响。根据分析结果,提出了系统排水孔布置的建议,得出了在相应的排水减压措施下衬砌厚度由原设计35cm减至25cm,这一建议已被采用,取得了巨大经济效益。

关 键 词:隧洞  外水压力  有限元分析  渗流场  系统排水  综合修正系数
文章编号:1672-3031(2003)03-0200-07
修稿时间:2003-04-20

Study on external water pressure on lining of tunnel No 7 of south main of YRDP
LI Xue-chun,CHEN Zhong-hu,CHEN Ping and XU Xin. Study on external water pressure on lining of tunnel No 7 of south main of YRDP[J]. Journal of China Institute of Water Resources and Hydropower Research, 2003, 1(3): 200-206
Authors:LI Xue-chun  CHEN Zhong-hu  CHEN Ping  XU Xin
Affiliation:Department of Structures and Materials , IWHR, Beijing 100038, China;Department of Structures and Materials , IWHR, Beijing 100038, China;Department of Structures and Materials , IWHR, Beijing 100038, China;Department of Structures and Materials , IWHR, Beijing 100038, China
Abstract:The comprehensive correction coefficients were introduced to determine the external water pressure on lining of tunnel No 7 of the south main of Yellow River Diversion Project (YRDP) in Shanxi Province. In the calculation, the single revision coefficient specified in the Design Code was not used. The initial seepage was obtained and the permeability tensors of different rock strata and the intensity of infiltration were derived by means of back analysis according to the water levels in boreholes and the locations of spring.The external water pressure was obtained by applying finite element analysis (FEA), taking into consideration the relative permeability of concrete and rock mass and the effects of drainage hole and grouting. Based on the results, some suggestions were put forward. The thickness of concrete lining could be reduced from 35 cm to 25 cm. This proposal was accepted and a large amount of investment was saved.
Keywords:tunnel  external water pressure  FEA   seepage field  drainage system  comprehensive correction coefficient.
本文献已被 CNKI 维普 万方数据 等数据库收录!
点击此处可从《中国水利水电科学研究院学报》浏览原始摘要信息
点击此处可从《中国水利水电科学研究院学报》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏