岩滩碾压混凝土围堰河槽段施工系统分析
引用本文:樊启祥,曾国顺. 岩滩碾压混凝土围堰河槽段施工系统分析[J]. 中国三峡建设, 2003, 10(3): 29-31
作者姓名:樊启祥  曾国顺
作者单位:中国三峡总公司,中国三峡总公司 湖北宜昌 443133,湖北宜昌 443133
摘    要:较详细叙述和分析了岩滩水电站碾压混凝土围堰施工从混凝土生产,经自卸汽车运输入仓到上坝碾压的混凝土施工一条龙系统,及碾压混凝土仓面细部结构与仓面混凝土施工质量控制。

关 键 词:岩滩水电站 碾压混凝土 围堰 汽车运输 混凝土施工
文章编号:1006-6349(2003)03-0029-03
修稿时间:2003-01-13

Analysis of Construction System for RCC Cofferdam at Yantan
FANG Qi-xiang and ZENG Guo-shun. Analysis of Construction System for RCC Cofferdam at Yantan[J]. China Three Gorges Construction, 2003, 10(3): 29-31
Authors:FANG Qi-xiang and ZENG Guo-shun
Abstract:In this paper a streamlined production system for the RCC cofferdam at the Yantan hydroelectric scheme is analyzed, including concrete production, transportation by trucks from batching plant to the working fronts, dumping, spreading, compaction, as well as arrangement of detailed structures and quality control.
Keywords:Yantan hydroelectric project  RCC  cofferdam  hauling by truck  construction technology.  