矿山法扩挖盾构隧道修建地铁车站技术
引用本文:廖鸿雁.矿山法扩挖盾构隧道修建地铁车站技术[J].都市快轨交通,2011,24(6):81--85.
作者姓名:廖鸿雁
作者单位:广州市地下铁道总公司 广州510380
摘    要:论述矿山法扩挖盾构隧道这种修建地铁车站的新技术.广州地铁6号线东山口站利用该技术,成功解决了盾构过站和修建车站站台隧道之间的矛盾.结合东山口站的工程实践,分析该技术的特点及良好的使用效果.

关 键 词:地铁  车站  矿山法  盾构隧道  站台隧道  先站后隧  先隧后站  开挖  扩挖
修稿时间:2013/12/12 0:00:00

Mining Excavation Adopted to EnlargeShield Tunnels to Build a Metro Station
Liao Hongyan.Mining Excavation Adopted to EnlargeShield Tunnels to Build a Metro Station[J].Urban Rapid Rail Transit,2011,24(6):81--85.
Authors:Liao Hongyan
Affiliation:Liao Hongyan(Guangzhou Metro Corporation,Guangzhou 510380)
Abstract:Mining excavation adopted to enlarge shield tunnels to build a station is a new technique.This new technique has been used on Guangzhou metro Line 6,and has successfully overcome the contradiction between the shield’s passing through and the construction of platform tunnel.The paper summarizes the characteristics and striking effect of the technique during the whole course of construction of Dongshankou Station.
Keywords:metro  station  mining method  shield tunnel  platform tunnel  platform first tunnel second  tunnel first platform second  excavation  enlarge excavation