南京地铁中胜站明挖基坑降水设计与施工
引用本文:徐振龙,王炳华,胡云峰. 南京地铁中胜站明挖基坑降水设计与施工[J]. 工业建筑, 2005, 35(Z1): 577-581
作者姓名:徐振龙  王炳华  胡云峰
作者单位:中铁三局集团,太原,030001
摘    要:针对南京地铁中胜站典型的二元化地质概化模型,分析承压不完整井在非稳定流和干扰状况下的工作机理,提出了一套相对完善的计算设计方法,计算结果与施工监测结果基本吻合。该方法可为类似工程的设计和施工提供参考。

关 键 词:深基坑  地基降水  承压水  非稳定流  不完整井
修稿时间:2004-09-15

DESIGN AND CONSTRUCTION OF DEWATERING IN DEEP EXCAVATION FOR ZHONGSHENG SUBWAY STATION OF NANJING
Xu Zhenlong,Wang Binghua,Hu Yunfeng. DESIGN AND CONSTRUCTION OF DEWATERING IN DEEP EXCAVATION FOR ZHONGSHENG SUBWAY STATION OF NANJING[J]. Industrial Construction, 2005, 35(Z1): 577-581
Authors:Xu Zhenlong  Wang Binghua  Hu Yunfeng
Abstract:It is analyzed that the working principles of an imperfect confined water well subjected to nonsteady seepage and interfering conditions;and a set of relative perfect design and calculation methods are also proposed,whose results are basically agreed with monitoring results during construction.The methods may be a reference for the design and construction of similar projects.
Keywords:deep excavation dewatering pressure water non-steady seepage imperfect well  