某金矿全尾膏体充填与排放联合处置技术
引用本文:王建栋,吴爱祥,王贻明,王洪江,王勇,周勃.某金矿全尾膏体充填与排放联合处置技术[J].金属矿山,2015,44(11):12-16.
作者姓名:王建栋  吴爱祥  王贻明  王洪江  王勇  周勃
作者单位:1.北京科技大学土木与环境工程学院,北京 100083;2.金属矿山高效开采与安全教育部重点实验室,北京 100083
基金项目:* 国家自然科学基金项目(编号:51374034,51304011,51374035),“十二五”国家科技支撑计划项目(编号:2012BAB08B02)。
摘    要:针对国内某金矿原分级尾砂胶结充填存在的采场充填料浓度低、水泥耗量高以及尾矿库库容不足等诸多问题,对充填系统进行优化改造,提出了一种基于深锥浓密机的全尾膏体充填和堆存联合处置方案。改造后的充填系统运行过程中,选厂全尾砂经泵站打入深锥浓密机。需要充填时,深锥底流经两段卧式搅拌机与水泥混合,制备出膏体自流或泵送至采场。不需要充填时,底流由柱塞泵泵送至尾矿库进行膏体堆存。通过计算和实践证明:改造后的方案可节约充填成本1 399万元/a,节约尾矿排放成本1 040万元/a;尾矿排放浓度由35%提高至68%以上,增加了尾矿的堆积角,提高了尾矿库服务年限。全尾膏体充填和堆存联合处置方案可以很好地同时解决采空区充填和尾矿堆存2个难题,具有巨大的经济和社会效益,符合"绿色矿山"的建设理念。

关 键 词:充填系统  全尾膏体充填  尾矿膏体堆存  联合处置  优化改造

Co-disposal Technology Reconstruction of Paste Backfilling and Tailing Discharge in a Gold Mine
Wang Jiandong,Wu Aixiang,Wang Yiming,Wang Hongjiang,Wang Yong,Zhou Bo.Co-disposal Technology Reconstruction of Paste Backfilling and Tailing Discharge in a Gold Mine[J].Metal Mine,2015,44(11):12-16.
Authors:Wang Jiandong  Wu Aixiang  Wang Yiming  Wang Hongjiang  Wang Yong  Zhou Bo
Affiliation:1.School of Civil and Environmental Engineering,University of Science and Technology Beijing,Beijing 100083,China;2.State Key Laboratory of the Ministry of Education for High-efficient Mining and Safety of Metal Mines,Beijing 100083,China;
Abstract:For some problems such as low filling slurry concentration,high cement consumption and lack of tailings capacity of classified tailings cemented backfill in a gold mine in China,a co-disposal scheme of unclassified-tailings paste filling and stockpiling based on the deep cone thickener was proposed to improve and optimize existing filling system.During the operation of filling system post-improvement,all unclassified tailings from dressing plant were pumped into the deep cone thickener by first or multistage pumping station.When filling is required,thickener underflow is mixed with cement by two-stage horizontal mixer to produce paste which flow by gravity or pumped to stope.When filling is not required,underflow is transported to tailing pond for paste stockpiling by piston pump.The calculation and practice showed that the reforming scheme can save 13.99 million yuan filling cost and 10.4 million yuan tailings discharge cost per year.And,tailings discharge concentration was increased from 35% to 68% which contributes to increase the tailings stockpiling angle and prolong the service life of tailings pond.The co-disposal scheme of unclassified-tailings paste filling and stockpiling,according with the conception of “Green Mining”,can simultaneously realize goaf filling and tailings stockpiling.
Keywords:Filling system  Unclassified-tailings paste backfill  Tailing paste stockpiling  Co-disposal  Optimized reform