首页 | 官方网站   微博 | 高级检索  
     

盾构密封舱土压预测及优化控制智能策略
引用本文:曹 曦,邵 诚,安 毅.盾构密封舱土压预测及优化控制智能策略[J].煤炭学报,2015,40(12):2979-2986.
作者姓名:曹 曦  邵 诚  安 毅
作者单位:1. 大连理工大学; 2. 大连理工大学控制工程学院
基金项目:国家自然科学基金资助项目;中央高校基本科研业务费专项资金资助
摘    要:盾构掘进过程中开挖面压力失衡易导致地表塌陷或隆起的灾难性事故。由于密封舱土压的变化情况与开挖面压力密切相关,因此精确预测及控制密封舱土压是有效预防开挖面压力失衡的关键技术之一。为建立密封舱土压的预测模型,首先从机理上对密封舱土压与掘进参数的关系,特别是刀盘扭矩对土压的影响,做了详细分析,以此为基础确定了密封舱土压模型新的输入输出参数。然后建立了依据密封舱压力传感器数据、基于最小二乘支持向量机(LS-SVM)的土压预测模型。并且基于此预测模型,以密封舱内四点土压预测值与设定值偏差最小为优化指标,采用粒子群算法(PSO)对控制参数进行在线优化,实时控制密封舱土压平衡。最后结合现场施工数据进行了仿真对比分析,验证了模型的有效性和准确性,为准确预测和控制密封舱土压,保证掘进过程安全提供了技术支持。

关 键 词:盾构  土压平衡    LS-SVM  预测    PSO  控制  
收稿时间:2015-02-09

Earth pressure prediction and optimal control intelligent strategy for shield chamber
Abstract:During the process of shield excavating, the pressure unbalance of excavation surface is easy to cause the collapse or blow-out of ground surface, which may lead to disastrous accidents. Since the change of chamber earth pressure is closely related to the pressure of excavation surface, accurate prediction and control of chamber earth pressure is one of the key technologies to avoid the pressure unbalance of the excavation surface effectively. In order to establish the prediction model of chamber earth pressure, the relationships between the earth pressure and the excavating parameters, especially the influence of cutter torque on the earth pressure, were analyzed on the mechanism in detail firstly. On this basis, the new input and output parameters of earth pressure model were determined. Then, according to the data of pressure sensors on the clapboard, a prediction model of earth pressure was established based on the least squares support vector machine(LS-SVM). And based on the prediction model, by minimizing the deviation between the four predicted earth pressure and the setting values,the particle swarm optimization (PSO) was adopted to optimize the control parameters and ,therefore, the online balance control of earth pressure was realized . Finally, in order to verify the validity and accuracy of prediction model, simulation experiments and comparative analyses were carried out by using the on-site construction data. The proposed method provided the technical support for accurate prediction and control of chamber earth pressure and ensuring the safety in the excavating process.
Keywords:shield  earth pressure balance  LS-SVM  prediction  PSO  control
本文献已被 万方数据 等数据库收录!