首页 | 官方网站   微博 | 高级检索  
     

东莞水道特大桥钢管拱肋扣挂法施工线型控制
引用本文:高芒芒,许兆军,白玲,潘家英.东莞水道特大桥钢管拱肋扣挂法施工线型控制[J].中国铁道科学,2005,26(2):59-63.
作者姓名:高芒芒  许兆军  白玲  潘家英
作者单位:1. 铁道科学研究院,铁道科学技术研究发展中心,北京,100081
2. 铁道科学研究院,铁道建筑研究所,北京,100081
摘    要:针对东莞水道特大桥主桥结构(主跨拱肋采用钢管混凝土拱形空间桁架结构,主拱肋轴线采用悬链线)和扣挂法施工的特点,采用正装法进行主拱钢结构施工中的线型控制分析。在扣索索力调整阶段,将该扣索索力对结构的作用作为外荷载加在相应位置,已完成调索的扣索作为结构的一部分参与结构受力。索力调整的原则是,使各节段变位尽可能接近裸拱自重挠度,且使已完成调索的各扣索索力变化较小。施工阶段线型控制分析过程中,拱肋轴线始终在理想拱轴线附近。

关 键 词:拱桥  施工  钢管混凝土  扣挂法  线型控制
文章编号:1001-4632(2005)02-0059-05
修稿时间:2004年8月13日

Linetype Control of the Fastening Method Construction of Steel Tube Arch Rib for the Extra-large Bridge on Dongguan Watercourse
GAO Mang-mang,XU Zhao-jun,BAI Ling,PAN Ja-ying.Linetype Control of the Fastening Method Construction of Steel Tube Arch Rib for the Extra-large Bridge on Dongguan Watercourse[J].China Railway Science,2005,26(2):59-63.
Authors:GAO Mang-mang  XU Zhao-jun  BAI Ling  PAN Ja-ying
Affiliation:GAO Mang-mang~1,XU Zhao-jun~2,BAI Ling~1,PAN Jia-ying~2
Abstract:In terms of the main bridge structure of the extra-large bridge on Dongguan watercourse (with arch composed of spacial truss structure, and steel pipe concrete adopted for the arch rib of the main span and the catenary line is used as the axis of the main arch rib) and the characteristics of the fastening and suspension construction method, order-erecting method was employed to carry out the linetype control analysis on steel arch structure construction of the main span. During the period of adjusting the force of the fastening cable, the action of the fastening cable force on the structure was considered as the external load and was imposed on corresponding position. The fastening cable whose adjustment having been completed was involved in the mechanical behavior as a part of the structure. The principle for cable force adjustment is to make the displacement of each section as close to the self-weight deflection of the bare arch as possible, and to make the less change of each cable force whose adjustment having been completed. In the process of the linetype control analysis of the construction stage, the axis of the arch rib keeps round the ideal arch axis all the time.
Keywords:Arch bridge  Construction  Steel tube concrete  Fastening method  Linetype control
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司    京ICP备09084417号-23