正削式隧道门围岩和衬砌应力计算及设计方法研究
引用本文:张俊儒,仇文革.正削式隧道门围岩和衬砌应力计算及设计方法研究[J].岩土力学,2006,27(11):2071-2075.
作者姓名:张俊儒  仇文革
作者单位:西南交通大学 土木工程学院,成都 610031
摘    要:对无明显墙式结构的正削式隧道门,现行规范没有现成的设计方法及结构检算模式。采用三维有限元数值分析方法,针对两种在洞口段的不同施工方法(明挖工法和暗挖工法),对隧道门洞口段的力学特性及设计方法进行了研究。研究结果表明:洞口段长度取42 m进行整体设计比较合理;在洞口28 m范围内的浅埋段,拱顶围岩压力随着埋深的增大而逐渐增加,且暗挖工法产生的围岩压力最大,铁路规范计算结果次之,明挖工法产生的压力最小;采用明挖工法施工时,在纵向上,洞口段42 m范围内衬砌拱顶表现出纵梁弯曲特征,部分仰拱处于弯拉状态,内力呈空间效应,均需要对横、纵向内力进行结构检算;采用暗挖工法施工时,只需进行横向内力检算即可。在成洞条件允许的情况下,建议使用暗挖工法进行隧道洞口段施工,可有效改善隧道洞口段结构受力。

关 键 词:隧道  正削式隧道门  结构应力  数值模拟  设计方法  
文章编号:1000-7598-(2006)11-2070-05
收稿时间:2005-08-23
修稿时间:2005-11-29

Numeration analysis and design method research into surrounding rock and lining structural stress of up bamboo-truncating tunnel portal
ZHANG Jun-ru,QIU Wen-ge.Numeration analysis and design method research into surrounding rock and lining structural stress of up bamboo-truncating tunnel portal[J].Rock and Soil Mechanics,2006,27(11):2071-2075.
Authors:ZHANG Jun-ru  QIU Wen-ge
Affiliation:School of Civil Engineering, Southwest Jiaotong University, Chengdu 610031, China
Abstract:For up bamboo-truncating tunnel portal without obvious wall-style structure,there is no existent design method and structure checked mode in present code.In this paper,aiming at bored method and open-cut method for portal section,3D FEM numerical analysis method is adopted to study the mechanical behaviors and design method of tunnel portal section.The research results show that:Choosing 42 m as the length of portal section and designing as a whole could be reasonable;In the shallow burying section of the extension of 28 m,the surrounding rock pressure of lining crown increases with the increase of depth of tunnel;and pressure of the bored tunneling method tunnel is maximal,the calculation result following the method of the railway tunnel code is the second;and the pressure of the open-cut method is minimal;When taking open-cut method,in the longitudinal direction of the extension of 42 m of portal,the mechanical behaviors of lining crown shows some characters of stringer bending,part of crown is in bended-pulled state;the internal force shows a three-dimensional effect,and the internal force of the direction both transversal and longitudinal should be checked for structure;when taking bored method,the internal force checking is only considered for transversal direction;when the excavation condition allows,the bored method is suggested to do portal tunneling by the reason that this tunneling method can improve mechanical behaviors of tunnel portal structure effectively.
Keywords:tunnel  up bamboo-trnncating tunnel portal  structural stress  numerical simulation  design method