首页 | 官方网站   微博 | 高级检索  
     

布仑口-公格尔水电站总体布置设计
引用本文:余春海,代立新.布仑口-公格尔水电站总体布置设计[J].水力发电,2007,33(9):28-30,46.
作者姓名:余春海  代立新
作者单位:新疆水利水电勘测设计研究院,新疆,乌鲁木齐,830000
摘    要:布仑口-公格尔水电站是新疆盖孜河段的第一个梯级电站,主要建筑物有首部枢纽、引水隧洞和电站厂房。工程所处地区属高寒地区且地质、地形条件复杂,施工难度较大,为此,对总体布置进行了多方案比选,最终确定了设计方案,即首部坝址选在布仑口湖湖口下游约0.95 km处,坝型为粘土心墙砂砾石坝,引水隧洞选择下线方案,厂房采用地面厂房。

关 键 词:总体布置  高水头电站  长距离引水隧洞  布仑日-公格尔水电站
文章编号:0559-9342(2007)09-0028-03
修稿时间:2007-03-12

Design of General Layout of Bulungkol-Gongur Hydropower Station
Yu Chunhai,Dai Lixin.Design of General Layout of Bulungkol-Gongur Hydropower Station[J].Water Power,2007,33(9):28-30,46.
Authors:Yu Chunhai  Dai Lixin
Affiliation:Xinjiang Water Conservancy and Hydropower Investigation and Design Institute, Urumqi Xinjiang 830000
Abstract:The Bulungkol-Gongur Hydropower Station is the first cascade power station in the middle reach of Gez River in Xinjiang, which is composed of three parts, headraee scheme, water diversion tunnel and powerhouse of power station. The station is built in a very cold area with complicated landform and geological conditions, so that its construction is very difficult. The final design is decided with comparing several general layout alternatives, that is, the headraee dam is located in the downstream of Butungkol Lake, 0.95km distance to the mouth of the lake, and is a clay core-wall sandygravel dam. Its diversion tunnel adopts a down-line alternative and its powerhouse adopts the ground powerhouse.
Keywords:general layout  high-head power station  long-distance diversion tunnel  Bulungkol-Gongur Hydropower Station
本文献已被 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司    京ICP备09084417号-23

京公网安备 11010802026262号