石板山隧道衬砌施工技术
引用本文:钟享华,张红卫,张爱民.石板山隧道衬砌施工技术[J].铁道建筑技术,2008(4):41-44.
作者姓名:钟享华  张红卫  张爱民
作者单位:中铁二十二局集团石太客专铁路指挥部,北京,100000
摘    要:石太客运专线石板山隧道前长7505m,位于R=12000m曲线上,线间距由4.96m渐变至4.6m,断面变化处采用顺接过渡,设计为单洞双线隧道,是全线贯通的控制工程之一。通过对石板山隧道进口段衬砌施工实践,着重阐述衬砌各分项工程施工工艺和控制措施。

关 键 词:隧道衬砌  施工工艺  控制措施

Lining Construction Techniques for Shibanshan Tunnel
Zhong Xianghua,Zhang Hongwei,Zhang Aimin.Lining Construction Techniques for Shibanshan Tunnel[J].Railway Construction Technology,2008(4):41-44.
Authors:Zhong Xianghua  Zhang Hongwei  Zhang Aimin
Affiliation:(China Railway 22nd Bureau Group Co. Ltd. , Beijing 100000, China)
Abstract:The 7 505-meter-long Shi-Tai Passenger Railway Shibanshan Tunnel is at R = 12 000 m curve, line spacing contracting from 4.96 m to 4.6 m gradually, with cross-section changes adopting the aiding connection transition. The design is sole-hole double-deck tunnel, one of the all-line "run-through" control projects. Based on the lining construction practice of entrance section in Shibanshan tunnel, this paper focused on the construction techniques and control measures in every sub-project of the lining.
Keywords:tunnel lining  construction techniques  control measures