首页 | 官方网站   微博 | 高级检索  
     

益地水电站地下厂房布置
引用本文:梁剑,谭清林.益地水电站地下厂房布置[J].湖北水力发电,2014(12):31-33.
作者姓名:梁剑  谭清林
作者单位:中国水电顾问集团中南勘测设计研究院,湖北宜昌,443002
摘    要:益地水电站地下厂房所处地层岩性以中薄层变质石英砂岩为主,结合厂区建筑物布置、岩层走向、地质构造、地应力等对厂房纵轴线及洞室布置方式进行比较,最终确定厂房纵轴线及主要洞室布置方式。

关 键 词:益地水电站  地下厂房  纵轴线  洞室布置

Layout of the Underground Powerhouse of Yidi Hydropower Station
LIANG Jian,TAN Qinglin.Layout of the Underground Powerhouse of Yidi Hydropower Station[J].Hubei Water Power,2014(12):31-33.
Authors:LIANG Jian  TAN Qinglin
Affiliation:( Hydrochina Zhongnan Engineering Corporation, Yichang 443002, China)
Abstract:The underground powerhouse of Yidi Hydropower Station is located in rocks of thin-layered metamorphic quartz sandstone .Considering the arrangement of powerhouse structures , stratum trend , geological structure and ground stress , different schemes of axis direction and layout of the powerhouse are compared .Then the optimal scheme is deter-mined.
Keywords:Yidi Hydropower Station  underground powerhouse  longitudinal axis  layout