山区公路桥梁基桩嵌岩深度计算方法研究
引用本文:戴国亮,邓会元,高鲁超,竺明星,龚维明.山区公路桥梁基桩嵌岩深度计算方法研究[J].岩土工程学报,2018,40(Z2):225-229.
作者姓名:戴国亮  邓会元  高鲁超  竺明星  龚维明
作者单位:1. 东南大学混凝土及预应力混凝土结构教育部重点实验室,江苏 南京 210096;2.东南大学土木工程学院,江苏 南京 210096;3. 中国能源建设集团江苏省电力设计院有限公司,江苏 南京 211100
基金项目:国家自然科学基金项目(51478109,51678145); 中央高校基本科研业务费专项(2242015KT10008); 江苏省普通高校研究生科研创新计划资助项目(KYLX16_0239); 中国博士后科学基金面上项目(2017M611955); 中能建江苏院科技项目(32-JK-2016-001)
摘    要:嵌岩桩在山区高速公路建设中应用广泛,具有稳定性高、承载力大等特点,嵌岩深度对嵌岩桩的承载特性起到至关重要的作用。考虑嵌岩段顶部受剪力和弯矩组合作用下,引入Hoek-Brown准则,建立静力平衡方程,得到最小嵌岩深度的计算模型。结合实际工程案例,对比其他计算方法,论证了方法的可行性,对嵌岩桩设计具有一定的参考价值;同时,验证了采用四次多项式拟合岩石破坏面上切应力和法向应力之间的关系式满足精度和误差的要求。

关 键 词:山区高速公路  嵌岩桩  最小嵌岩深度  Hoek-Brown准则  
收稿时间:2018-07-22

Method for rock-socketed depth of highway bridge piles in mountain areas
DAI Guo-liang,DENG Hui-yuan,GAO Lu-chao,ZHU Ming-xing,GONG Wei-ming.Method for rock-socketed depth of highway bridge piles in mountain areas[J].Chinese Journal of Geotechnical Engineering,2018,40(Z2):225-229.
Authors:DAI Guo-liang  DENG Hui-yuan  GAO Lu-chao  ZHU Ming-xing  GONG Wei-ming
Affiliation:1. Key Laboratory of Concrete and Prestressed Concrete Structure of Ministry of Education, Southeast University, Nanjing 210096, China;2. School of Civil Engineering, Southeast University, Nanjing 210096, China;3.China Energy Engineering Group Jiangsu Power Design Institute Co., Ltd., Nanjing 211100, China
Abstract:The rock-socketed pile is widely applied in the construction of highways in mountain areas, which has the characteristics of high stability and large bearing capacity. The rock-socketed depth plays a crucial role in the bearing characteristics of rock-socketed piles. A static equilibrium equation is established to obtain the computational model for the minimum rock-socketed depth in which the Hoek-Brown criterion is introduced, and it takes the combination of shear force and bending moment into consideration at the top of rock-socketed section. The feasibility of the proposed method is demonstrated in comparison with other methods, and it may have certain reference value to the design of rock-socketed piles. At the same time, the relationship between shear stress and normal stress of the quartic polynomial fitting rocks is verified to meet the requirements of accuracy and error.
Keywords:mountain highway  rock-socketed pile  minimum rock-socketed depth  Hoek-Brown criterion  