千万吨矿井建设施工组织设计
引用本文:杨本生,张利,王如文,杨荣国,耿学良.千万吨矿井建设施工组织设计[J].煤炭科学技术,2012,40(4):6-9.
作者姓名:杨本生  张利  王如文  杨荣国  耿学良
作者单位:1. 河北工程大学资源学院,河北邯郸,056038
2. 河北工程大学资源学院,河北邯郸056038/霍州煤电集团有限责任公司,山西霍州031400
3. 霍州煤电集团有限责任公司,山西霍州,031400
基金项目:河北省自然科学基金资助项目
摘    要:基于千万吨矿井建设的复杂性和不确定性,为确保矿井建设总工期和建设质量,以井巷施工为核心,地面建筑和机电设备安装为辅助的原则,提出了2个施工组织设计方案。方案一,岩巷掘进速度为100m/月,煤层平巷为200m/月;方案二,岩巷掘进速度为120m/,月,煤层平巷为550m/月,同时有10个掘进工作面施工,其中含3条煤巷。综合施工进度指标、提升和运输水平以及国内技术现状等因素,论证分析得出方案一更为科学合理,并采用方案一指导现场施工作业。

关 键 词:千万吨矿井  施工组织  矿井建设  岩巷掘进

Design of Construction Organization for Mine with Annual Production Over 10 Mt
YANG Ben-sheng,ZHNAG Li,WANG Ru-wen,YANG Rong-guo,GENG Xue-liang.Design of Construction Organization for Mine with Annual Production Over 10 Mt[J].Coal Science and Technology,2012,40(4):6-9.
Authors:YANG Ben-sheng  ZHNAG Li  WANG Ru-wen  YANG Rong-guo  GENG Xue-liang
Affiliation:1(1.School of Resources,Hebei University of Engineering,Handan 056038,China; 2.Huozhou Coal and Electric Power Group Corporation Ltd.,Huozhou 031400,China)
Abstract:Based on the complexity and uncertainty of the mine construction with an annual production of 10 Mt,in order to ensure the total mine construction period and construction quality,taking the mine roadway construction as the key and taking the surface building and the electromechanical equipment installation as the supplementary principle,two construction organization design plans were provided.The heading speed of the mine rock roadway would be 100 m per month and the driving speed of the mine seam gateway would be 200 m per month.As for the second plan,the heading speed of the mine rock roadway would be 120 m per month and the driving speed of the mine seam gateway would be 550 m per month.Meanwhile there would be 10 driving faces in construction,including three seam gateways.With the comprehensive demonstration and analysis on the construction schedule index,hoisting and transportation,the domestic technical status and other factors,the first plan would be more scientific and rational,the first plan was determined to guide the site construction operation.
Keywords:mine with annual production over 10 Mt  construction organization  mine shaft construction  gateway driving