黄埔发电厂1-4号机组补水率偏高的治理
引用本文:陈建华.黄埔发电厂1-4号机组补水率偏高的治理[J].广东电力,2006,19(11):73-75.
作者姓名:陈建华
作者单位:广东粤华发电有限责任公司,广州,510731
摘    要:对广东粤华发电有限责任公司(黄埔发电厂)14号机组补水率偏高的现象进行了分析研究,认为导致补水率偏高的原因主要是锅炉排污量偏大、发电机内冷水水箱溢流及疏水系统阀门泄漏。为此,采取了相应的改进措施,有效地提高了机组运行的经济性。

关 键 词:发电补水率  连续排污  内冷水水箱溢流
文章编号:1007-290X(2006)11-0073-03
修稿时间:2006年5月8日

Tackling of high make-up water rate of Units 1 - 4 in Huangpu Power Plant
CHEN Jian-hua.Tackling of high make-up water rate of Units 1 - 4 in Huangpu Power Plant[J].Guangdong Electric Power,2006,19(11):73-75.
Authors:CHEN Jian-hua
Abstract:The high make-up water rate of demineralized water for Units 1-4 in Guangdong Yuehua Power Generation Co.,Ltd.(Huangpu Power Plant) was investigated.It was concluded that the problem was mainly caused by the large blowdown flow rate of the boilers,overflow of the generator inner cooling water tank as well as valve leakage of the drainage system.Corresponding measures were taken to effectively improve the economic efficiency of the units.
Keywords:make-up water rate of power generation  continuous blowdown  overflow of inner cooling water tank