首页 | 官方网站   微博 | 高级检索  
     

陷落柱影响区综放工作面煤壁及顶板超前注浆加固技术
引用本文:田杰.陷落柱影响区综放工作面煤壁及顶板超前注浆加固技术[J].山东煤炭科技,2020(6):54-56,59.
作者姓名:田杰
作者单位:山西晋煤集团赵庄二号井,山西 长治 047100
摘    要:为了解决综放工作面过陷落柱期间煤壁片帮、顶板冒顶的问题,以赵庄二号井2309工作面为背景,通过槽波及钻探确定陷落柱影响范围,采用深浅孔配合的注浆加固方案对陷落柱影响区煤体及顶板进行加固。注浆加固后工作面煤壁平整且未出现冒顶现象,工作面推进速度得到明显提高,为正常区的80%以上。

关 键 词:综放  陷落柱  加固

Advance Grouting Reinforcement Technology of Coal Wall and Roof in Fully Mechanized Caving Face of Collapse Column Affected Area
Tian Jie.Advance Grouting Reinforcement Technology of Coal Wall and Roof in Fully Mechanized Caving Face of Collapse Column Affected Area[J].Shandong Coal Science and Technology,2020(6):54-56,59.
Authors:Tian Jie
Affiliation:(Shanxi Jin Coal Group Zhaozhuang No.2 Well,Shanxi Changzhi 047100)
Abstract:In order to solve the problem of coal wall and roof falling during the period of fully mechanized top coal caving face passing through the collapse column,taking the 2309 working face of Zhaozhuang No.2 Well as the background,the influence scope of the collapse column is determined by the trough wave and drilling,and the coal body and roof in the area affected by the collapse column are reinforced by the grouting reinforcement scheme of deep and shallow holes.After grouting reinforcement,the coal wall of the working face is flat and there is no roof falling,and the advancing speed of the working face is obviously increased,which is more than 80%of the normal area.
Keywords:fully mechanized caving  collapse column  reinforcement
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司    京ICP备09084417号-23

京公网安备 11010802026262号