Optimization model of truck flow at open-pit mines and standards for feasibility test
作者姓名:YingZhang  YongZhao  QiweiLu  WenliXu
作者单位:DepartmentofAutomation,TsinghuaUniversity,Beijing100084,China
基金项目:This work was financially supported by the National Key Technologies RD Program in the 10th five-year plan (No.2001BA609A-08).
摘    要:In order to increase production efficiency at open-pit mines, on the basis of linear programming, a practical mathematical model for optimizing truck flow was developed, which improved the traditional fixed manual schedule method. The model has advantages from linear programming and objective programming, makes most handling points working at full capacity and keeps an optimized ratio between trucks and excavators. For ensuring feasibility of the model in practical production, four standards for feasibility test were proposed. The model satisfied all the standards. The application in a large scale open-pit iron mine indicated that the model reduced the number of required trucks by 10% compared with the fixed manual schedule method.

关 键 词:最优化模型  开凿机  开挖  可行性实验  线性规划  货车调度系统

Optimization model of truck flow at open-pit mines and standards for feasibility test
YingZhang YongZhao QiweiLu WenliXu.Optimization model of truck flow at open-pit mines and standards for feasibility test[J].Journal of University of Science and Technology Beijing,2004,11(5):389-393.
Authors:Ying Zhang  Yong Zhao  Qiwei Lu  Wenli Xu
Abstract:In order to increase production efficiency at open-pit mines, on the basis of linear programming, a practical mathematical model for optimizing truck flow was developed, which improved the traditional fixed manual schedule method. The model has advantages from linear programming and objective programming, makes most handling points working at full capacity and keeps an optimized ratio between trucks and excavators. For ensuring feasibility of the model in practical production, four standards for feasibility test were proposed. The model satisfied all the standards. The application in a large scale open-pit iron mine indicated that the model reduced the number of required trucks by 10% compared with the fixed manual schedule method.
Keywords:open-pit mine  truck flow  linear programming  mathematical model  feasibility